Split any installed price into six parts and the arguments about cost start to make sense.
- The sealed unit and frame. On a straightforward roof window swap this is often the largest single line. On flat-roof and lantern work, where a kerb has to be built and an opening formed, it usually is not.
- Forming and trimming the opening. Cutting the roof, transferring the load off whatever has been removed, and building the timber the unit will sit on.
- Weathering. Flashing kits on a pitched roof, membrane dressing and upstand detailing on a flat roof. This is the part that decides whether the installation is still dry in ten years.
- Access. Scaffolding, tower hire, and on larger glass, a lift or a crane. Purely a function of where the roof is and what is underneath it.
- Making good inside. Insulating and boarding the reveal, plastering it, and decorating. A separate trade visit, and a real cost.
- Paperwork. Building Control notification, and a structural engineer’s calculations where the opening needs them.
Two quotes for the same house usually differ on the last three, not the first. That is worth knowing before you conclude that one installer is expensive. A price that only covers the glass, the hole and a bit of flashing will always look better on paper than one that carries scaffolding, a plastered reveal and the notification, and you will pay the difference later either way.